PSA Project Work Breakdown Structure Manually Schedule for weekend?

$
0
0

Hello All,

I am using PSA module to manage projects. Generally our projects do not require working over the weekend. However sometime very rarely we might want to schedule a task on off working days. Please can someone help me in setting this up?

I have already tried going to work breakdown structure and change the "Task Mode" from "Automatic Schedule" to "Manually Schedule". However when I try to select the weekend the system will still set the day to next Monday. Any help in this regard will be much appreciated.

Thanks

Dev