Hi,
I'm looking for a simple way to add a very long service activity (7 days +) that would exclude the week-ends.
The issue here is that if I define a service that has for example 7 days, the service calendar will count Saturday and Sunday as being worked when they are not leaving me 2 days short. I have attached an example where I would expect the calendar to skip Sunday and add the last day on Monday but it only gives me a warning that my resources is scheduled outside of his working hours.
I know that I could create 2 separates activities (one being 5 days and another 2 days the next week) but it would add a lot of extra work when we having longer service (>20 days).
Is there a more efficient way to do this ?